Things started out great - Jeff was responsive, promptly scheduled an in person consult for a quote, and left making us feeling good about hiring him for the job. He said that it would likely take 3-4 days for completion.
The day before he was set to start, we had windows replaced and stucco frames removed, and had flagged that we might need to delay the paint job until the stucco was repaired. He told us he could take care of this as an add-on.
By the end of day 3, the stucco was still untouched and the majority of the exterior area had still not painted. We needed the project to be completed before an event, but by the end of the second week, we could tell that this was not going to be possible. Timing was poorly managed, there was a lack of crew (most days it was just him) and yet every day we were told that he needed 1 more day to finish.
2 weeks in, we found another contractor that completed the stucco work within 24 hours as things still weren't looking good with Jeff. He had his "crew" show up to the house and say that they weren't comfortable with the height, on two separate occasions.
In the end, the project took 3 weeks and had still had many areas that needed to be touched up or missed. We decided to break ties, and complete the rest of the work ourselves. We did add on the garage from the original quote, but it's shocking that this would've required 2 additional weeks from the original estimate.