New home build with ICF to the trusses
We hired a company to build the shell of our house with ICF, put the trusses and sheeting on and the floor joists in. We did get all of the services required but they neglected to read the drawings correctly. Since this was our first time building with ICF we were not aware that the ledger boards were to go on before the house was poured. It was miserable and expensive for us to do it later. All the company said was "oh well, it's easy and cheap for you to do it yourself". HA were they wrong. They also neglected to use a level when they were bracing the walls upstairs. The walls are leaning outwards by 1 3/4" from top to bottom. Of course this wasn't found until we started framing the interior. So many modifications have had to be done due to their shoddy workmanship.
- Approximate cost of services:
- $90,000.00