Timeline;
July 4 agree on new electrical panel.
July 11, permit goes through.
July 29, new panel installed.
August 28, finishing touches applied.
Almost 2 months from start to finish....
Really.........

Approximate cost of services:
$4,000.00
1 of 2 people found this review helpful.
Was this review helpful?

Previous versions of this review:

Lynne Harvey from West Vancouver
Lynne Harvey from West Vancouver
2 reviews West Vancouver, BC
2/10

New Electrical Panel

Timeline;
July 4 agree on new electrical panel.
July 11, permit goes through.
July 29, new panel installed.
August 28, finishing touches applied.
Almost 2 months from start to finish....