Basement and bathroom reno/repair
General Contractors review in
Toronto
Tuppin Construction's staff left to go on a three week vacation about a week after the job started. The tradespeople did not show up as scheduled; work was generally completed OK after lots of ""encouraging"" from the homeowner. Small things were consistently left undone. The biggest problem was the floor replacement, which took more than four months to source and install; and then it was installed incorrectly (it was damaged). It took another two months to get replacement materials and to finish the job, and at that point I didn't want them in my house any longer, even though many little things remain unfinished."
Was this review helpful?